Y.M.C.A.

Ponca City Aquatic and Family Center — YMCA

 
     
 
 
 

 

Ponca City Aquatic and Family Center — YMCA

 

South-West View of the Ponca City Aquatic and Family Center — YMCA


SITE PLAN | MAIN LEVEL | UPPER LEVEL


Relief Greets New Bids For P.C. YMCA Center

By BEVERLY BRYANT
News Staff Writer


The first new bids for work on the Ponca City Aquatic and Family Center — YMCA were opened Thursday and greeted with relief.

Ponca City officials and leaders of Lambert Construction of Stillwater, the construction manager at risk for the project, said Friday they are pleased with the bids that were opened for the first six parcels of work.

"The bids are almost $20,000 below our budgeted price for the work that was to be completed in those six bid packages," said Stephen Mitchell of Lambert Construction of Stillwater. "We feel really good about the efforts of the city, the architect and Lambert to get the numbers closer to being in the budget."

Mitchell, who is a vice president of Lambert Construction and manager of the project, said Thursday's bids reflect an even greater savings when compared to bids that were opened for the project in July 2008.

"From then to now, with the value engineering we've all done, the numbers are really at least $500,000 less than the numbers we had in July for the work in those six bid packages," Mitchell said.

Thursday's bids covered six pieces of the project:

  • Stormwater Pollution Prevention Program and temporary fencing;
     
  • Earthwork and site demolition;
     
  • Site utilities and storm water;
     
  • Stacked block retaining walls;
     
  • Paving asphalt and concrete, and
     
  • Sidewalks and miscellaneous concrete.

After Lambert Construction completes its analysis of the bids, it will present its recommendations to the Ponca City Board of Commissioners for final approval.

Three bids that were opened in July were for the total project and came in between $25.4 million and $26.1 million, nearly $10 million more than engineers' estimates.

City Commissioners voted in July to reject all of the bids, and in a joint meeting with the YMCA's Board of Directors voted to hire a construction manager at risk to work with the city and the architect to perform value engineering on the project and rebid the project in separate packets.

In addition, Ponca City residents voted in December to extend a half-cent sales tax funding the project for up to five years to increase the money available for the project.

Friday morning Mayor Homer Nicholson said city officials, through the construction manager at risk, are still looking at the bid numbers and are doing due diligence to evaluate all of the bids.

"We were encouraged that the numbers appeared to be coming in less than our projections, but we really haven't gotten the numbers down to where we can do any interpretations," Nicholson said. "There are caveats that we have to go through and we need to analyze the numbers."

The national economic slump also is working in the city's favor, he said.

"We do plan to move as fast as possible to get all of our other bid packages out as soon as we can during the down economy, to take advantage of low materials costs and the extra availability of skilled craftsmen," Nicholson said.

"When our first bids came in, we were at the worst of times. Now we may be at the best of times. We're pretty optimistic that we have some pretty good numbers," the mayor said.

City Manager Craig Stephenson said Friday he was very happy with the number of companies that submitted bids this time.

"That was a good sign. I was pleased with the numbers as they came in. We are still working with those numbers with the construction manager at risk, but they are much better than the numbers we got July 10, which is good for us to know," Stephenson said.

The city manager said he expected to have the numbers analyzed by the first part of the week.

"At this point, we are very happy with the numbers and hope those continue on into the next phase," he said.

Stephenson said it was difficult to compare the new bids to those received in July, since the July bids were not broken down in the same way.

"And with the value engineering we've done, we're not really comparing apples to apples," Stephenson said.

Stephenson said more bid packages for subsequent work will be opened in March.